Supersession & cutover

How a released Revision or Replacement Part phases over, the cutover fields you tune per item, and how MRP and Get Method honor supersession downstream.

Releasing a Revision or Replacement Part creates a from the old item to the new item. Configure phase-over behavior with cutover fields on the affected item.

A Version edits the existing item and creates no supersession. A New Part has no predecessor and also creates none. Only change types that derive a new item from an existing one create supersessions.

NOTE

Only Revision and Replacement Part supersede.

The rule is the predecessor: a Revision phases the old revision over to the new one, and a Replacement Part phases the affected part over to the new number. Version and New Part have no old item to redirect, so release skips supersession for them entirely.

Cutover fields

Set these on a Revision or Replacement Part affected item before you release.

FieldType
How planning treats the old item. See the modes below. Defaults to Consume First.
When the old item stops being usable. Empty means no planned discontinuation.
When the successor becomes effective for redirect. Empty means effective immediately at release.

Supersession modes

The controls how planning handles the old item:

ModeBehavior
Consume FirstExhaust on-hand of the old item, then redirect new demand to the successor.
Prefer NewRedirect new demand to the successor immediately.
Stock OnlyKeep only a minimum service reserve of the old item; no production use.
No StockDrop the old item from planning entirely.
NOTE

Only Consume First and Prefer New redirect demand.

Those two modes tell planning to route the old item's demand — times its conversion factor — to the successor. Stock Only and No Stock govern the old item's own stocking rather than redirecting to a successor.

How downstream honors it

On or after the successor-effectivity date, two systems apply the supersession:

  • MRP redirects planned demand for the old item to the successor, applying the conversion factor and collapsing multi-hop chains (if A was superseded by B and B by C, demand routes straight to C).
  • Get Method substitutes the successor onto Buy and Pull bill-of-materials lines when a new job is created, recording the source item so the substitution is traceable.
HEADS UP

Release never touches work already in flight.

Existing stock stays on the old item, and jobs already created keep the exact materials and method version they were built against. Open documents follow the same rule: a purchase order, sales order, or quote line that names the old item keeps it; nothing warns or rewrites it at release. Supersession only steers forward planning — a job created after the successor's effectivity date picks up the new item; one created before it does not shift. That's what makes releasing safe on a busy floor.